Megger Insulation Testing & Motor Diagnostics

Before you replace, rewind or restart a motor after a long shutdown, you need reliable readings. We run insulation resistance, polarization index, winding balance and run tests, and hand you a written summary of the results.

+971 56 445 8874 · +971 56 668 3688

An insulation resistance test measures how well the insulation between the windings and the earthed frame stops leakage current. A Megger applies 500 V or 1000 V DC for a set time. A low reading points to moisture, contamination or damage — the most common reason an RCD trips when a motor starts.

One reading is not enough. The polarization index (PI) compares the 10-minute and 1-minute readings and shows whether insulation is damp or dirty even when the spot value looks acceptable. We also measure each phase’s resistance with a micro-ohmmeter, because unbalance points to an inter-turn short or a loose connection.

These tests are a mandatory part of every repair and rewind in our workshop, and are also offered on their own — for motors that need an assessment before a decision, or as periodic checks in a preventive maintenance programme.

When do you need insulation and diagnostic testing?

RCD trips on start

Especially after a shutdown or in humid weather; condensation may have lowered insulation.

Before restarting a motor that has stood idle

Running a motor with damp insulation can turn a dryable problem into burnt windings.

Repeated overload trips

Per-phase current and winding resistance show whether the cause is the motor, the connections or the load.

Before deciding to repair or replace

Diagnosis defines the repair scope and whether rewinding makes sense before money is spent.

After water ingress or washing

To confirm insulation is back within safe limits after drying.

As preventive maintenance

Comparing periodic readings reveals insulation decline before a failure stops production.

Our testing steps

  1. Safe isolation & visual check

    Lockout/tagout (LOTO), then a visual check of the terminal box and connections.

  2. Insulation resistance & PI

    Winding-to-earth insulation with a 500 V or 1000 V DC Megger, and polarization index.

  3. Winding resistance balance

    Phase-to-phase resistance with a micro-ohmmeter to find inter-turn shorts or loose terminals.

  4. Running checks

    Where possible: per-phase current with a True-RMS clamp meter, thermal imaging of terminals and frame, vibration and bearing temperature.

  5. Summary & recommendation

    Readings against reference limits, with a clear recommendation: run, dry, repair or rewind.

Reference limits we use

Each reading is compared with limits published in international standards, and the reference is shown next to the reading in the summary:

IEEE 43
Insulation resistance and PI for low-voltage windings: minimum 5 MΩ and PI ≥ 2.0.
NEMA MG-1
Phase current unbalance; above about 10 % needs investigation.
ISO 10816
Vibration severity (mm/s RMS): good ≤ 2.8, alert 2.8–7.1, danger > 7.1 for roughly 15–75 kW machines.
NETA MTS
Thermography ΔT between similar components: 1–3 °C watch, 4–15 °C repair soon, > 15 °C repair immediately.
IEC 60364-6
Low-voltage installations up to 500 V: test at 500 V DC, minimum 1 MΩ.

What you get

  • 500 V / 1000 V DC insulation resistance test and polarization index
  • Phase winding ohmic balance measurement
  • Assembly, no-load current check and final safety inspection
  • Mechanical clearance, bearing temperature and vibration checks
  • A documented test summary with readings and a recommendation
  • Online stage and readings tracking with your reference code

Frequently asked questions

What is an acceptable motor insulation reading?

We use IEEE 43: for low-voltage windings, at least 5 MΩ and a PI of 2.0 or more. The value is read together with PI, winding balance and the motor’s condition.

What is the difference between a 500 V and a 1000 V test?

Test voltage is chosen by the equipment’s operating voltage. Low-voltage installations up to 500 V are usually tested at 500 V DC; for the common 400 V motors in the UAE we use 500 V or 1000 V depending on the motor.

My motor trips the RCD after a shutdown — is it burnt?

Not necessarily. Moisture and condensation are a frequent cause. If winding resistance is balanced there is no inter-turn short, and the windings can be oven-dried and re-tested before restart.

Do you test on site?

Yes. As part of our on-site support we can run insulation, current and thermal imaging checks at your facility, scoped once we know the equipment and location.

Do I get a written report?

Yes — a documented test summary with readings, and you can follow the stage and readings through the tracker on our website.

Ready to diagnose your equipment?

Based in Sharjah, serving all UAE emirates. Scope and schedule are confirmed for every request before work starts.