An insulation resistance test measures how well the insulation between the windings and the earthed frame stops leakage current. A Megger applies 500 V or 1000 V DC for a set time. A low reading points to moisture, contamination or damage — the most common reason an RCD trips when a motor starts.
One reading is not enough. The polarization index (PI) compares the 10-minute and 1-minute readings and shows whether insulation is damp or dirty even when the spot value looks acceptable. We also measure each phase’s resistance with a micro-ohmmeter, because unbalance points to an inter-turn short or a loose connection.
These tests are a mandatory part of every repair and rewind in our workshop, and are also offered on their own — for motors that need an assessment before a decision, or as periodic checks in a preventive maintenance programme.
When do you need insulation and diagnostic testing?
RCD trips on start
Especially after a shutdown or in humid weather; condensation may have lowered insulation.
Before restarting a motor that has stood idle
Running a motor with damp insulation can turn a dryable problem into burnt windings.
Repeated overload trips
Per-phase current and winding resistance show whether the cause is the motor, the connections or the load.
Before deciding to repair or replace
Diagnosis defines the repair scope and whether rewinding makes sense before money is spent.
After water ingress or washing
To confirm insulation is back within safe limits after drying.
As preventive maintenance
Comparing periodic readings reveals insulation decline before a failure stops production.
Our testing steps
Safe isolation & visual check
Lockout/tagout (LOTO), then a visual check of the terminal box and connections.
Insulation resistance & PI
Winding-to-earth insulation with a 500 V or 1000 V DC Megger, and polarization index.
Winding resistance balance
Phase-to-phase resistance with a micro-ohmmeter to find inter-turn shorts or loose terminals.
Running checks
Where possible: per-phase current with a True-RMS clamp meter, thermal imaging of terminals and frame, vibration and bearing temperature.
Summary & recommendation
Readings against reference limits, with a clear recommendation: run, dry, repair or rewind.
Reference limits we use
Each reading is compared with limits published in international standards, and the reference is shown next to the reading in the summary:
- IEEE 43
- Insulation resistance and PI for low-voltage windings: minimum 5 MΩ and PI ≥ 2.0.
- NEMA MG-1
- Phase current unbalance; above about 10 % needs investigation.
- ISO 10816
- Vibration severity (mm/s RMS): good ≤ 2.8, alert 2.8–7.1, danger > 7.1 for roughly 15–75 kW machines.
- NETA MTS
- Thermography ΔT between similar components: 1–3 °C watch, 4–15 °C repair soon, > 15 °C repair immediately.
- IEC 60364-6
- Low-voltage installations up to 500 V: test at 500 V DC, minimum 1 MΩ.
What you get
- 500 V / 1000 V DC insulation resistance test and polarization index
- Phase winding ohmic balance measurement
- Assembly, no-load current check and final safety inspection
- Mechanical clearance, bearing temperature and vibration checks
- A documented test summary with readings and a recommendation
- Online stage and readings tracking with your reference code
Frequently asked questions
What is an acceptable motor insulation reading?
We use IEEE 43: for low-voltage windings, at least 5 MΩ and a PI of 2.0 or more. The value is read together with PI, winding balance and the motor’s condition.
What is the difference between a 500 V and a 1000 V test?
Test voltage is chosen by the equipment’s operating voltage. Low-voltage installations up to 500 V are usually tested at 500 V DC; for the common 400 V motors in the UAE we use 500 V or 1000 V depending on the motor.
My motor trips the RCD after a shutdown — is it burnt?
Not necessarily. Moisture and condensation are a frequent cause. If winding resistance is balanced there is no inter-turn short, and the windings can be oven-dried and re-tested before restart.
Do you test on site?
Yes. As part of our on-site support we can run insulation, current and thermal imaging checks at your facility, scoped once we know the equipment and location.
Do I get a written report?
Yes — a documented test summary with readings, and you can follow the stage and readings through the tracker on our website.